|
LIEN LAWS
The state’s
constitution provides for the filing of liens against real
property to secure payment to those supplying labor or
materials on a project. The lien law does not apply to
federal or state public works.
Lien Defined A
lien is a right to secure payment for work or materials
furnished to improve real property (land or buildings). A
properly filed lien results in an unpaid obligation recorded
against the title to the property similar to a mortgage on a
building. If the obligation is not satisfied, the sale of
the property may be forced to satisfy the lien.
Who May Lien?
To be able to file a lien to secure an amount die, a
contract with the owner is not necessary. Those without a
contract with the owner who supply labor, professional
design or surveying services, materials or furnishes rental
equipment at the site of improvement may also file.
Liens may be
filed against the real property or, in the case of
subcontractors, against funds owed to the party that is
obligated to the subcontractor.
The process to
perfect or properly complete a lien filing may require
several specific steps filed with various entities, in an
exact time frame. Courts generally require strict compliance
with the provisions of the lien law and will dismiss
improperly filed liens.
The following
is an overview of the key elements of the lien law. It is
not meant to be a complete description of the steps
necessary to perfect a lien. Legal advice should be obtained
for specific help in protecting and asserting lien rights.
FILING CLAIMS
Those entitled
to file a lien against real property must file the lien with
the Clerk of the Superior Court in the county where the
project is located. The lien must be filed within 120 days
after the last furnishing of labor or materials at the
project.
The Claim of
Lien must contain the following information:
-
the name
and address of the person claiming the lien;
-
the name
and address of the owner of the property at the time the
claim is filed;
-
a
description of the property upon which the lien is
claimed;
-
the name
and address of the person with whom the claimant
contracted for the furnishing of labor or materials;
-
the date
when labor or materials were first furnished by the
claimant;
-
the date
when labor or materials were last furnished; and
-
a general
description of the labor performed or materials
furnished and the amount claimed.
An action in
court against the owner for enforcement of the lien must be
started within 180 days after the last furnishing of labor
or materials at the project.
A lien filed
against a property may be discharged by any of the following
methods:
-
The
claimant may acknowledge the satisfaction of the lien
indebtedness before the clerk of the superior court;
-
The owner
may submit an instrument of satisfaction from the lien
claimant to the clerk of the superior court;
-
The failure
by the claimant to enforce the lien within the time
required;
-
The filing
in the office of the clerk of the superior court, a
court judgment, or a decree showing the dismissal of the
claimants lien;
-
The
depositing of an amount equal to the lien with the clerk
of the court; or
-
The filing
of a surety bond in the amount of 125% of the lien.
To file a lien
on funds, the subcontractor must serve a notice of claim on
the party owing the funds, as well as the owners of the
property and all others above the subcontractor in the
contractual chain. The subcontractor’s notice of claim of
lien shall contain the following information:
-
the name
and address of the person claiming the lien;
-
a general
description of the property involved;
-
the name
and address of the person with whom the claimant
contracted;
-
the name
and address of each person for whom subrogation rights
are claimed (applicable if the claimant is second or
third tier subcontractor);
-
a general
description of the contract and the person against whose
interest the lien is claimed; and
-
The amount
claimed.
The notices of
claims of liens by first, second, or third tier
subcontractors must be on a form substantially, as shown in
Exhibit 1.
The party who
receives notice of claim must withhold payment in the amount
of the claim or face liability to the claimant.
FILING A NOTICE OF CONTRACT
A general
contractor may be able to cut off the lien rights of
sub-contractors by posting a “Notice of Contract” at the
project and filing the notice with the county clerk within
30 days of obtaining a building permit. The form of the
Notice of Contract shall contain the following information:
-
the name
and address of the contractor;
-
the name
and address of the owner of the property at the time the
notice is filed;
-
a general
description of the real property to be improved; and
-
The name
and address of the person or entity filing the notice.
The
subcontractor’s lien rights can be re-established if a
“Notice of Subcontract” is sent to the general contractor
and is posted at the project. The form of the Notice of
Subcontractor shall contain the following information:
-
the name
and address of the subcontractor;
-
a general
description of the real property where the labor was
performed or the materials furnished;
-
a general
description of the subcontractor’s contract including
the names of the contracting parties;
-
a
description of the labor and materials furnished; and
-
a request
that the subcontractor be notified in writing by the
contractor within five days of each payment by the
contractor to the first tier subcontractor, the date of
payment and the period covered.
The lien rights
of lower tier subcontractors (second, third, etc.) can be
cut off by the general, even if they have filed notices of
subcontract, if the general notifies them within five days
of any payments made to the first tier subcontractor.
FALSE CLAIMS
If any person
receiving payments for an improvement to real property
furnishes a false written statement of the sums due or
claimed for labor or materials furnished to the property,
the person shall be guilty of a Class 1 misdemeanor.
Additionally,
any person who knowingly causes, or attempts to cause, the
filing of a lien or other document that is either not
authorized by statue or intended to hinder, harass, or
wrongfully interfere with another, shall be guilty of a
Class 1 misdemeanor.
|